Thursday, February 25, 2010

Day 27 - Continue with cable ladder

Date: 23/2/2010

I was having trade school yesterday.

0630 - Started with George on cable ladder

If without the all the gas and aircon piping, the installation for the cable ladder should be pretty easy. Squeezing our body and climbing on top of the piping, at some point of time, has became necessary - which supposed to be an unsafe act. With a little bit of planning, all these inconvenience could be avoided.

George was becoming impatient with me lack of tools for the job. For several times, he urged me to get my own tools. He told me to get from a cheap harware store in Pooraka. I was hesitating because I'm still waiting for the tool allowance from the government which would be in voucher. Unfortunately, that would be in May. In my opinion that's too long ahead. Therefore, I've decided to get the tools by this week.

1600 - Finished