I was assigned to work with PSG Boffa & Russo and scheduled to rock up at Adelaide Entertainment Centre @ 7am for induction. Unfortunately, I was given a wrong contact by Peer and was at the wrong entrance. So I was late for the induction and therefore not inducted. The site foreman, Ted was quite pissed. Nevertheless, I was still allowed to be remained in the site. I met with Simo - the electrician and Ben - the 3rd year apprentice.

0820 - Laying and installing conduit into trench. Learn how to cut conduit with other means - like using catenary cable.

1030 - Removes concrete.

1200 - Back to PEER for Boffa & Russo's online induction.

1330 - Finish and didn't go back to site.

Interestingly, the workers in a construction site have a common habit, not dissimilar to those in Malaysia, they like to make sentence with vulgar words. Especially Ted, the F word appeared in almost each sentences that came out from his mouth. He meant no harm, just his way of talking.

No comments:

Post a Comment